NEW QUESTION # 11
Which of following best defines Outcomes?
- A. Measurable improvement resulting from outcomes perceived as advantage
- B. Completed set of project outputs
- C. New operational state achieved after transition of capability in live operations
- D. Deliverable of a project
Answer: C
NEW QUESTION # 12
Which of the following defines an Emergent programme?
- A. Must do programmes often due to result of an external event and aimed to avoid negative implications
- B. Programme focused on transforming the way business functions
- C. Translation of political priorities into a programme to refine and deliver desired changes
- D. Evolved from concurrent, individual projects with need to ensure compliance to organization strategy
Answer: D
NEW QUESTION # 13
Which of the following is NOT an MSP Governance Theme?
- A. Learning from Experience
- B. Leadership and Stakeholder Engagement
- C. Quality Management
- D. Organization
Answer: A
NEW QUESTION # 14
Which of the following is Not one of MSP defined levels of stakeholder engagement?
- A. Active Consultation
- B. Keep informed
- C. Formally Approve
- D. Maintain Interest
Answer: C
NEW QUESTION # 15
Through which document programmes establish the context in which risks will be identified and assessed and responses planned and implemented?
- A. Risk register
- B. Issue register
- C. Quality and assurance plan
- D. Programme plan
Answer: A
NEW QUESTION # 16
Which of following is not responsibility of Programme Office?
- A. Ensuring the control and management frameworks are effectively implemented
- B. Providing regular updates on progress to SRO
- C. Repository of programme information
- D. Risk and Issue tracking
Answer: B
NEW QUESTION # 17
Who reviews Business Case?
- A. SRO
- B. Programme Manager
- C. Sponsoring Group
- D. BCM
Answer: D
NEW QUESTION # 18
Which type of cost is associated in training, moving and supporting an operational unit?
- A. Business change and transition cost
- B. Capital cost
- C. Benefits realization cost
- D. Programme management cost
Answer: A
NEW QUESTION # 19
As the influence of a stakeholder increases, it is recommended that a 'higher' level of engagement is appropriate. Which of the following describes this increasing engagement?
- A. Active consultation, keep informed, maintain interest
- B. Maintain interest, active consultation, keep informed
- C. Keep informed, maintain interest, active consultation
- D. Keep informed, active consultation, maintain interest
Answer: C
NEW QUESTION # 20
When it is found that an acceptable Business Case is not emerging, which of the following is NOT one of the normal options?
- A. Close the Programme
- B. Seek further funding for the programme
- C. Design a Blueprint that is less ambitious
- D. Find a different approach to delivering the Blueprint
Answer: B
NEW QUESTION # 21
Which of the following is an influencer type of stakeholder?
- A. Management board
- B. Supplier
- C. Media
- D. Business partner
Answer: C
NEW QUESTION # 22
Which of following is False?
- A. Stakeholders can change during the lifecycle of programme
- B. Instead of having individual stakeholders, it is better to divide them in suitable categories
- C. Stakeholder profiles identifies and lists each stakeholder properties
- D. Stakeholder profiles are created under stakeholder maps
Answer: D
NEW QUESTION # 23
Which of the following is not an Input to delivering the capability?
- A. Project dossier
- B. Blueprint
- C. Project outputs
- D. Business Case
Answer: C
NEW QUESTION # 24
Which of the following is a programme management principle?
- A. Remaining aligned with corporate strategy
- B. Quality and assurance management
- C. Leadership and stakeholder management
- D. Realizing the benefits
Answer: A
NEW QUESTION # 25
Which of the following is not true about programme control?
- A. Programme control minimizes impact of ambiguity
- B. Programme control provides supporting activities to refine and improve delivery
- C. Programme control justifies continuance of programme
- D. Programme control defines reporting mechanism
Answer: D
NEW QUESTION # 26
Which of following is input for 'managing the tranches'?
- A. Assurance review reports
- B. Programme Brief
- C. Approval to proceed
- D. Programme preparation plan
Answer: C
NEW QUESTION # 27
Which of the following is NOT set out by the Programme Brief?
- A. Analysis of the options available
- B. Key resources needed
- C. Risks and issues
- D. Estimated cost
Answer: A
NEW QUESTION # 28
MSP is best suited for which programme?
- A. Launching new products
- B. Simple programme with defined outcomes and strong governance in place
- C. Technically complex but with defined outputs
- D. Programme for long term societal change
Answer: D
NEW QUESTION # 29
Who is accountable for confirming programme closure?
- A. SRO
- B. Sponsoring group
- C. BCM
- D. Programme Manager
Answer: A