Topic 1
  • Quality Management: Understand quality assurance and control processes to ensure that programme deliverables and outcomes meet or exceed defined quality standards.
Topic 2
  • Risk and Issue Management: Acquire advanced knowledge of identifying, assessing and managing risks and issues that can impact a programme's success.
Topic 3
  • Benefits Realization: Master techniques for identifying, defining, tracking and realizing the full range of benefits a programme is intended to deliver, with a focus on benefits measurement and realization.
Topic 4
  • Governance and Control: Gain an in-depth understanding of programme governance, including setting up and maintaining governance structures, accountability mechanisms and assurance processes to deliver programme success.
Topic 5
  • Problem Solving: Develop expertise in addressing complex programme management challenges and resolving issues efficiently and effectively.
Topic 6
  • Stakeholder Engagement: Learn how to effectively manage diverse stakeholders, including executives, sponsors, team members, suppliers and customers, with advanced communication and relationship-building skills.

 

NEW QUESTION # 11
Which of following best defines Outcomes?

  • A. Measurable improvement resulting from outcomes perceived as advantage
  • B. Completed set of project outputs
  • C. New operational state achieved after transition of capability in live operations
  • D. Deliverable of a project

Answer: C


NEW QUESTION # 12
Which of the following defines an Emergent programme?

  • A. Must do programmes often due to result of an external event and aimed to avoid negative implications
  • B. Programme focused on transforming the way business functions
  • C. Translation of political priorities into a programme to refine and deliver desired changes
  • D. Evolved from concurrent, individual projects with need to ensure compliance to organization strategy

Answer: D


NEW QUESTION # 13
Which of the following is NOT an MSP Governance Theme?

  • A. Learning from Experience
  • B. Leadership and Stakeholder Engagement
  • C. Quality Management
  • D. Organization

Answer: A


NEW QUESTION # 14
Which of the following is Not one of MSP defined levels of stakeholder engagement?

  • A. Active Consultation
  • B. Keep informed
  • C. Formally Approve
  • D. Maintain Interest

Answer: C


NEW QUESTION # 15
Through which document programmes establish the context in which risks will be identified and assessed and responses planned and implemented?

  • A. Risk register
  • B. Issue register
  • C. Quality and assurance plan
  • D. Programme plan

Answer: A


NEW QUESTION # 16
Which of following is not responsibility of Programme Office?

  • A. Ensuring the control and management frameworks are effectively implemented
  • B. Providing regular updates on progress to SRO
  • C. Repository of programme information
  • D. Risk and Issue tracking

Answer: B


NEW QUESTION # 17
Who reviews Business Case?

  • A. SRO
  • B. Programme Manager
  • C. Sponsoring Group
  • D. BCM

Answer: D


NEW QUESTION # 18
Which type of cost is associated in training, moving and supporting an operational unit?

  • A. Business change and transition cost
  • B. Capital cost
  • C. Benefits realization cost
  • D. Programme management cost

Answer: A


NEW QUESTION # 19
As the influence of a stakeholder increases, it is recommended that a 'higher' level of engagement is appropriate. Which of the following describes this increasing engagement?

  • A. Active consultation, keep informed, maintain interest
  • B. Maintain interest, active consultation, keep informed
  • C. Keep informed, maintain interest, active consultation
  • D. Keep informed, active consultation, maintain interest

Answer: C


NEW QUESTION # 20
When it is found that an acceptable Business Case is not emerging, which of the following is NOT one of the normal options?

  • A. Close the Programme
  • B. Seek further funding for the programme
  • C. Design a Blueprint that is less ambitious
  • D. Find a different approach to delivering the Blueprint

Answer: B


NEW QUESTION # 21
Which of the following is an influencer type of stakeholder?

  • A. Management board
  • B. Supplier
  • C. Media
  • D. Business partner

Answer: C


NEW QUESTION # 22
Which of following is False?

  • A. Stakeholders can change during the lifecycle of programme
  • B. Instead of having individual stakeholders, it is better to divide them in suitable categories
  • C. Stakeholder profiles identifies and lists each stakeholder properties
  • D. Stakeholder profiles are created under stakeholder maps

Answer: D


NEW QUESTION # 23
Which of the following is not an Input to delivering the capability?

  • A. Project dossier
  • B. Blueprint
  • C. Project outputs
  • D. Business Case

Answer: C


NEW QUESTION # 24
Which of the following is a programme management principle?

  • A. Remaining aligned with corporate strategy
  • B. Quality and assurance management
  • C. Leadership and stakeholder management
  • D. Realizing the benefits

Answer: A


NEW QUESTION # 25
Which of the following is not true about programme control?

  • A. Programme control minimizes impact of ambiguity
  • B. Programme control provides supporting activities to refine and improve delivery
  • C. Programme control justifies continuance of programme
  • D. Programme control defines reporting mechanism

Answer: D


NEW QUESTION # 26
Which of following is input for 'managing the tranches'?

  • A. Assurance review reports
  • B. Programme Brief
  • C. Approval to proceed
  • D. Programme preparation plan

Answer: C


NEW QUESTION # 27
Which of the following is NOT set out by the Programme Brief?

  • A. Analysis of the options available
  • B. Key resources needed
  • C. Risks and issues
  • D. Estimated cost

Answer: A


NEW QUESTION # 28
MSP is best suited for which programme?

  • A. Launching new products
  • B. Simple programme with defined outcomes and strong governance in place
  • C. Technically complex but with defined outputs
  • D. Programme for long term societal change

Answer: D


NEW QUESTION # 29
Who is accountable for confirming programme closure?

  • A. SRO
  • B. Sponsoring group
  • C. BCM
  • D. Programme Manager

Answer: A